Construction update

Major Delivery Information

Concrete:

The following major deliveries are due for the Kiln Pit Hill Wind Farm construction.

Met Mast foundation works:

Met mast concrete delivery 24.10.11 - this will involve approximately 12 concrete wagons throughout the day

Turbine foundation works:

10.11.11 - turbine 6 concrete delivery
16.11.11 - turbine 5 concrete delivery
24.11.11 - turbine 4 concrete delivery
01.12.11 - turbine 3 concrete delivery
07.12.11 - turbine 2 concrete delivery
13.12.11 - turbine 1 concrete delivery

Each of the above turbine concrete deliveries will involve approximately 50 concrete wagons through out the day for each delivery.

Please note that dates may change due to site / weather conditions. Wherever possible, we will aim to revise dates on the web page should there be any changes. Changes will also be communicated via the text messaging service.

The text messaging service advises local residents of key construction activities such as road closures and deliveries. If you would like to be contacted in this way please register your mobile telephone number by texting ‘Kiln Pit Hill Wind Farm' your name and postal address (including postcode) to 07748182167 or email us at kilnpithill@npower-renewables.com.