Construction timetable

Key Project Dates

 

Please note the dates are subject to change. 

 

November 2010


Highway upgrade works and site interface works begin


February 2011


Site access tracks installed


Throughout 2011


Foundations laid and civil and electrical works are completed


Late 2011


Grid connection works and electrical works completed


Early 2012


Turbine installation and commissioning


Mid 2012


Project complete


Little Cheyne Court Wind Farm, Kent