Progress and the next steps

 

1Submission of Section 36 Application February 2011
2Public Consultation PeriodFebruary – April 2011
3Local Authority Consultation PeriodFebruary – July 2011
4Scottish Ministers Decision (if no further information or public inquiry required)November 2011
5Construction Period (if approved) 2013 – 2015
6Wind farm operational2015 onwards


footnote: Future dates are subject to change