Project timeline

Below is a list of the key milestones of the Atlantic Array Offshore Wind Farm project during the development phase.

These timings may change as the project progresses.

Quarter 2 2010Scoping report submission
Quarter 4 2011Formal public consultation on the Atlantic Array wind farm
Mid 2012

Formal consultation with statutory bodies on the Atlantic Array wind farm

2012

Wind Farm planning application submission to the Infrastructure Planning Commission.


If we are successful in gaining consent, Atlantic Array Offshore Wind Farm first generation could be as early as 2016.