Your settings for cookies and pixels on rwe.com

Select which cookies and pixels we are allowed to use. Please note that some cookies are necessary for technical reasons and must be enabled in order to maintain the functionality of our website. If you would like to benefit from every service on our website, please consider that you need to choose every cookie category. For more information, please refer to our Privacy Policy.

    • Maintain the stability of the website.
    • Save your log-in data.
    • Allow to improve the user experience.
    • They provide advertisements that are relevant to your interests.
    • They allow you to share interesting content directly with your social media network.

You can change your cookie and pixel settings on rwe.com at any time via our Privacy Policy.

Imprint

Show Details
Select all Confirm selection

RWE Generation SE

Commercial operation commences at Glen Noe Hydro

RWE Image
  • 2MW Run-of-river scheme successfully completed
  • Provision of £3K fund per annum for local community

Perth, 26 February 2021

Consented by Argyll & Bute Council in September 2016, RWE’s 2MW Glen Noe Hydro Scheme, located within the Glen Noe Estate, near Loch Etive in the west of Scotland, is now operational.

Construction of the powerhouse, 3km of buried pipeline and three intake weirs for the run-of-river scheme began in 2019 and, following completion of the grid connection in January, commissioning was successfully completed in mid-February 2021.

The scheme has the capacity to provide sufficient renewable electricity to power up to the equivalent of 1,436 average homes each year.  In addition, RWE will provide a community fund of £3,000 for each year for the operational lifetime of the project to Taynuilt Community Council.

Mary Drury, RWE Head of UK Hydro, said: “Following a successful construction phase, we are delighted that Glen Noe is now operational. Hydro has proved its longevity in the renewables business and so the commissioning of a further hydro scheme will play a crucial role in enabling Scotland to fulfil and maintain its clean energy future ambition to reach net zero carbon by 2045.

“RWE now operates 14 hydropower schemes across Scotland, all constructed to ensure that environmental constraints are strictly adhered to. For Glen Noe, this included ensuring that nearby nesting Golden Eagles were not disturbed during construction.”

RWE is the UK’s second largest power producer, generating over 12% of all electricity in the UK. In Scotland the company operates over 480MW of installed renewable capacity across 26 hydro and onshore wind sites and Scotland’s first commercial-scale offshore wind farm: Robin Rigg in the Solway Firth. RWE also operate a 55MW biomass combined heat and power district heating plant at Markinch; the Glenrothes Energy Network officially opened in April 2019 and is the first 100% renewable biomass power district heating network of its kind in Scotland.

For more information on Glen Noe visit: https://uk-ireland.rwe.com/locations/glen-noe-hydro-power-scheme

Downloads

RWE successfully completes onshore construction works for Triton Knoll Offshore Wind Farm

07.10.2021

Read more

Strong partnership for Greece: RWE and PPC form Joint Venture to realise renewable energy projects

07.10.2021

Read more

Wind farm Jüchen A 44n: all six turbines taken off the grid as a precautionary measure

01.10.2021

Read more