Your settings for cookies and pixels on rwe.com

Select which cookies and pixels we are allowed to use. Please note that some cookies are necessary for technical reasons and must be enabled in order to maintain the functionality of our website. If you would like to benefit from every service on our website, please consider that you need to choose every cookie category. For more information, please refer to our Privacy Policy.

    • Maintain the stability of the website.
    • Save your log-in data.
    • Allow to improve the user experience.
    • They provide advertisements that are relevant to your interests.
    • They allow you to share interesting content directly with your social media network.

You can change your cookie and pixel settings on rwe.com at any time via our Privacy Policy.

Imprint

Show Details
Select all Confirm selection
STA02-autarkie-zwischenlager-am-kraftwerk-biblis
STA02-autarkie-zwischenlager-am-kraftwerk-biblis

Documentation Management and Project Management

Autarky of the interim storage facility at biblis power plant

Client

RWE Nuclear GmbH

Location

Germany

Expertise

Feasibility Study, Documentation Management, Project Management

 

The Biblis nuclear power plant in Hesse was in operation until 2011 and is currently being decommissioned. Due to a law regulating the reorganization of the responsibility for nuclear waste disposal, the rights and obligations relevant for the business operation of the interim storage at the Biblis site have been transferred to the newly founded Company for temporary storage (BGZ). To enable an independent operation of the storage facility, it is necessary to ensure the functional autarky of it.

RWETI was assigned as operative project manager for support services within the scope of this customer-led project. The services comprise ongoing contract management, including the selection, instruction and monitoring of any additional subcontractors, participation in the planning and implementation of a self-sufficiency timetable concept as well as quality assurance.

After completion of the project, RWETI experts check and control the final documentation and are responsible for the acceptance of the construction work.

Our Services

  • Procurement of planning basis as preliminary work for general planner
  • Participation in the development of the concept for planning and realization of the autarky timetable
  • Coordination and control of design, approval and implementation planning 
  • Involvement of experts in the planning process
  • Support in submitting the building application
  • Quality assurance of the concept for planning and implementation documents
  • Preparation for execution 
  • Property monitoring
  • Acceptance of construction work
  • Control of final documentation