Rheinfelden (Baden)

Scope of the Project

The Rheinfelden Electrolyser Project is a renewable hydrogen production project located in Rheinfelden (Baden), Germany. The facility will consist of a 100 MW electrolyser (2 times 50 MW) and will primarily supply renewable hydrogen to industrial consumers in Germany. The project will use electricity from the grid, supported by renewable energy sources PV and wind generation.

The project will connect to Germany’s hydrogen core network, enabling hydrogen transport to customers in Germany and over the time facilitating cross-border hydrogen transport to neighbouring countries including France, Switzerland, Austria and Liechtenstein.

Map of the H2 Cluster South-West, showing hydrogen infrastructure across regions in France, Switzerland, and Germany.

Click on the image to zoom

The project contributes to the development of a comprehensive Western European hydrogen network and secure a sustainable industrial supply.


Approval Procedures

The project has been included on the European Union’s Projects of Common Interest and Projects of Mutual Interest (PCI/PMI) list and is progressing through engineering and permitting activities.

The permit granting process will be carried out in accordance with German and European regulatory requirements.

A black binder lies open on a wooden desk with white papers fanned under warm sunlight, giving a calm, orderly impression.

Public Participation

Stakeholder engagement and public consultation activities will be conducted throughout project development.

Information concerning consultation periods, project documentation and stakeholder events will be made available on this website as required by the permitting process.

A navy blue fabric tote bag with the white text "RWE" hangs over a gray upholstered conference chair, repeated along a row.

Contact us about our project

Your contact details for queries

Fields marked with * are mandatory.

Further information on data protection can be found in our data protection.


PCI / Funding

The Rheinfelden project is included on the Second Union List of Projects of Common Interest (PCI) and Projects of Mutual Interest (PMI) adopted in April 2026 under reference number 9.18.3. The project has been identified as a strategic energy infrastructure project supporting the development of an integrated European hydrogen network and contributing to the EU’s decarbonisation objectives.

A key feature of the project is that its location near the border in the tri-border region between Germany, Switzerland, and France provides excellent access to European hydrogen customers, thereby ensuring a stable and sustainable industrial supply. 


Project schedule

RWE Image
rwe-research

Pre-Feasibility Study

09/2023 - 11/2023

RWE Image
rwe-process-course-management-2

Feasibility study and conceptual development
(Pre-FEED)

10/2026 - 09/2027

RWE Image
rwe-electrolyzer

Project Maturation (FEED),
Permitting and FID

Phase 1: 10/2027 - 01/2029
Phase 2: 10/2027 - 09/2030

A simple deep blue square on a white background, embodying minimalist design.
icon-helmet

Project Execution Time

Phase 1: 01/2029 - 11/2031
Phase 2: 09/2030 - 05/2033

RWE Image
rwe-technical-services-2

Commissioning

Phase 1: 11/2031
Phase 2: 5/2033

RWE Image
rwe-hydrogen

Operation

Phase 1: from 12/2031 (50 MW)
Phase 2: from 06/2033 (50 MW) 

You might also be interested in

Hydrogen

How RWE is actively helping to shape the age of hydrogen.

Read more

H₂@Hydro

Hydrogen electrolysis by hydropower.

Read more

Expansion Project RWE Epe-Hydrogen Storage

We are not standing still and are planning further expansion stages for Epe-H2 storage facilities.

Read more